What did your last implementation actually retire? If nothing comes to mind, that is the answer.

Cover of Built to Be Used

The most common way a large IT investment fails is that the new system is added to the organisation rather than substituted into it. Nothing stops. The workload goes up, and the business case quietly stops being true. One question tests for it. Which report is no longer produced. Which reconciliation is no longer performed. … Read more

Everyone is using the system. Almost nobody is using it while the work is happening.

Cover of Built to Be Used

Adoption reporting typically measures completeness: what proportion of the work was recorded in the system. The more revealing measure is timing. When did the entry happen, relative to the event it describes? A system used correctly but always retrospectively is not carrying the work. It is functioning as a reporting layer over an unchanged process, … Read more

The implementation failures that cost the most are the ones you will not find for two years.

Cover of Built to Be Used

They are not dramatic. They are quiet, competent adaptations that leave every formal indicator intact. Which is why acceptance risk needs a third dimension beyond likelihood and impact. If this happens, how would the organisation find out, and when? A risk that announces itself is manageable almost regardless of its likelihood. A system nobody can … Read more

“Users may resist the new system.” If that sentence is in your risk register, you do not have a risk. You have an anxiety.

Cover of Built to Be Used

It contains no cause, no specific behaviour, no consequence and no group. It cannot be assessed for likelihood, cannot be assigned to anybody meaningfully, and cannot be closed except by assertion. A usable acceptance risk states three things. The cause: something identifiable about the design, the process, the environment or the distribution of burden. The … Read more

The project was recorded as a success. The benefit never arrived. Both statements are true.

Cover of Built to Be Used

An implementation produces outcomes at four levels, and only one of them is normally contracted. The technical outcome: the system exists and functions within agreed parameters. The operational outcome: people can use it to perform their work, including the interruptions, exceptions and time pressure the process documentation left out. The behavioural outcome: they do. The … Read more